|
Electrical Service Distribution Systems
For new facilities with multiple buildings, the electrical service
shall typically be received from the local utility at a single location.
Electrical service to buildings at the facility shall be extended
on a customer-owned distribution system. The use of either a medium
voltage, or a 440V distribution system shall be considered. The distribution
system design choice shall be based on the facility’s layout,
loads, etc. Power for emergency and standby systems shall be provided
from a centrally located generator serving multiple buildings, or
from separate generators installed in each building. Life-cycle costing
analysis shall be performed to back up distribution system design
choices.
The electrical distribution system shall meet the requirements of
the state agency code and the National Electrical Code. Pay particular
attention to the requirements of providing emergency power; - emergency
power to end life safety devices shall be provided from the emergency
power source as an unbroken distribution system separate from the
normal distribution system. Note: multiple automatic transfer switches
shall be utilized when serving emergency and standby loads from an
emergency generator.
Most of the larger existing State facilities have normal power distributed
by an existing State-owned underground distribution system. Power
for emergency and standby systems is typically provided from generators
installed within each building, or from a centrally located generator
serving numerous buildings. Electrical service for new buildings in
these existing facilities shall be extended from the existing State-owned
distribution systems. The existing site distribution will dictate
the design of a new building’s normal and emergency power distribution
systems. It is the responsibility of the system designer to verify
existing system capacity when adding new building loads to an existing
State-owned distribution system.
When calculating the electrical service and feeder sizes for buildings,
pay particular attention to the connected load, standard power factor,
wiring standard and distance of complete layout plan.
The majority of system voltages presently used within buildings include
220/230V, 440/230 V, and 440 Delta. For large motor loads and large
lighting loads, 440volt systems shall typically be used.
For building services where the code requires ground fault protection
on the main service disconnect, ground fault protection shall also
be provided on the next level feeder breakers, to aid the coordination.
Set points for the distribution system’s overcurrent and ground
fault trip adjustments (electronic trip circuit breakers and protective
relays) shall be addressed. The system designer shall provide the
set points, or coordinate with the equipment manufacturer to provide
them. If the equipment manufacturer is to provide the set points,
the system designer shall provide information as required for the
manufacturer to perform the coordination study. The system designer
shall approve the set point recommendations and shall verify that
the devices have been properly set.
The consultant shall work with the architect to ensure that adequate
accessible indoor space is identified for distribution equipment that
is to be installed indoors.
For new or remodeled buildings, make sure that an electrical meter
that measures total building kWh and kW demand is provided.
Power and signal systems shall be provided between buildings as separate
manhole and ductbank systems. Spare conduits for each system shall
be provided. The consultant shall inquire about the long-range plans
for the site, and shall size the ductbanks from the distribution point
accordingly.
The program statement for new facility or building projects shall
be reviewed, and may specify additional distribution system requirements,
such as providing redundant generators or emergency feeders, sizing
generators to back up the entire facility, providing equipment to
parallel generators with the utility, or providing closed-transition
switching.
|